Oracle 1Z0-129 exam is a valuable certification for professionals who want to validate their knowledge and skills in Primavera P6 2021 Enterprise Project Portfolio Management. 1Z0-129 exam covers various topics related to project management, portfolio management, and resource management, and is recognized globally. It is an ideal credential for individuals who want to advance their careers in project management and for employers who want to hire candidates with expertise in using the Primavera P6 software.
NEW QUESTION # 16
Where are risk response plans captured?
- A. In the Risk Scoring Matrix
- B. In the Risk Register
- C. In the Activity Notebook for Risk
- D. In the Project Notebook for Risk
Answer: B
NEW QUESTION # 17
Cost accounts are hierarchical, and .
- A. are applicable to all projects in the EPS
- B. are created and managed at the Project level
- C. are assigned to users with security
- D. are assigned in Project Details
Answer: C
NEW QUESTION # 18
The Total Spending Plan Tally for a project is the sum of the Spending Plans assigned to .
- A. each Work Breakdown Structure (WBS) element in the project
- B. each immediate child Work Breakdown Structure (WBS) element
- C. each project in the Enterprise Project Structure (EPS)
- D. each immediate parent Work Breakdown Structure (WBS) element
Answer: C
NEW QUESTION # 19
You are developing a reporting strategy for a customer who requires monthly reports showing cost variance. The customer has two requirements.
1. Each report must come from Primaver
a.
2. Each month''s report must become a "snapshot" for legal traceability purposes. Which P6 R8 solution addresses each of the customer''s requirements?
- A. Send reports directly to printers at all user locations
- B. Send generated report to content repository
- C. Archive printed reports in files under security
- D. Email monthly report to distribution list
Answer: C
NEW QUESTION # 20
Your customer wants to copy a Shell template and include their Project Cost Sheet and Funding Sheets in the new template.
Identify two modules that must be selected when performing the copy action
- A. Cost Sheet
- B. Funding Sheet
- C. Cash Flow
- D. Commitment Funding Sheet
- E. Schedule of Values
Answer: A,B
NEW QUESTION # 21
Identify the true statement regarding the EPS page in P6 R8.
- A. You can copy a project on the EPS page and paste it into another EPS node.
- B. Any user can now copy projects on the EPS page regardless of the user,s Security profile.
- C. Only application administrators have the privilege to copy/paste projects.
- D. You cannot copy projects on the EPS page - this must still be done in the Client.
Answer: A
NEW QUESTION # 22
Select the true statement regarding the ability to create projects.
- A. Any Project Manager can create a project.
- B. Any user can create a project
- C. Any Responsible Manager can create a project.
- D. Any Admin Super user can create a project.
Answer: C
NEW QUESTION # 23
You are a portfolio manager. You opened a portfolio and you refreshed the filter. However, some of the projects that were previously in the portfolio are no longer there. What happened?
- A. You no longer have sufficient project-level security to view the "missing" project,s data.
- B. The projects were deleted when the filter was refreshed.
- C. The value of the code assigned to the missing projects has changed.
- D. Your web interface license was revoked to allow other users to interface with the projects.
Answer: D
NEW QUESTION # 24
What is the process that a System Administrator executes to provide access to Primavera for a new hire?
- A. Open the Resources window. Select "Add", and populate all Resource details.
- B. navigate to Projects. Select a Project and select "Shared" access mode in the Open Project dialog
- C. Choose Admin>Admin Preferences. Select the "User Fields tab and define a Resource for the user.
- D. Choose Admin>Users. Select "Add", and then populate all fields In User details.
Answer: D
NEW QUESTION # 25
Identify two use cases for Shell template.
- A. Create a new Shell by copying the Shell template.
- B. Push changes out to Shells as part of the change control process.
- C. Add Member Companies across multiple Shells.
- D. Manage Group Permissions across multiple Shell types.
Answer: B,D
NEW QUESTION # 26
Identify a relevant use case for applying a Must Finish By date to a project.
- A. Compare Must Finish By date to Actual Finish Date to negotiate realistic Finish dates
- B. Apply Must Finish By dates to shorten the duration of the schedule
- C. Compare Scheduled Finish to Must Finish By dates to negotiate realistic Finish dates
- D. Apply Must Finish By dates to build case for requesting resources
Answer: A
NEW QUESTION # 27
You are a Portfolio Manager looking for a new portfolio that you manually created. You have clicked the Group By drop-down list in Portfolios. Which option should you select to quickly find your portfolio?
- A. User Filtered Portfolio
- B. User Portfolio
- C. Global Filtered Portfolio
- D. Global Portfolio
Answer: A
NEW QUESTION # 28
You have completed and tested designs in the staging environment. Your project team feels that the design is ready to be brought into the production environment. Identify the first step in this process.
- A. Delete user data in staging environment.
- B. Export the design to a local directory.
- C. Delete staging data in production environment.
- D. Create the Design Bundle in staging Environment.
Answer: B
NEW QUESTION # 29
Select two true statements regarding Calendars.
- A. Activity type determines whether the activity uses Resource Calendars for scheduling.
- B. Activity Calendars are managed by individual Resources.
- C. Project Calendars are available for the current project only.
- D. Global Calendars are available to a subset of projects.
- E. Only a limited number of calendars can be created
Answer: A,E
NEW QUESTION # 30
You have added steps and links to create a sub-workflow. Identify the required next action.
- A. Complete sub-workflow properties.
- B. Group the selected sub-workflow steps.
- C. Ungroup selected sub-workflow steps.
- D. Add trigger elements.
Answer: B
NEW QUESTION # 31
What is the significance of setting "Summarize project based on high-level resource planning"?
- A. Summarized project data will be monetized.
- B. Summarized project data will reflect top-down plans.
- C. Summarized project data will reflect bottoms-up plans.
- D. Summarized project data will reflect actuals pushed from another application.
Answer: B
NEW QUESTION # 32
Select the true statement regarding Global Preferences in Primavera P6 EPPM Web Interface.
- A. Global Preferences are customized at the user level.
- B. Global Preferences are controlled by the System Administrator
- C. Global Preferences are shared among all users.
- D. Global Preferences are controlled by Global Security Profiles.
Answer: A
NEW QUESTION # 33
How can you change the data fields of folders and documents in Document Manager?
- A. Deploy a Document Attribute Form.
- B. Deploy a Shell Attributes Form in which the Document Manager is available.
- C. Deploy a Document type Business Process.
- D. Deploy the User Attributes Form.
Answer: C
NEW QUESTION # 34
View the Exhibit.
Which two statements about the date formula built on the Vendor Active Date field are true?
- A. It derives a number as the result.
- B. It derives a numeric value as the result.
- C. It derives another date as the result.
- D. It is an example of Date Difference.
- E. It is an example of date Add.
Answer: B
NEW QUESTION # 35
Identify one new feature in Release 8 related to Resource Management.
- A. Role teams
- B. Resource GANTT chart
- C. Resource teams
- D. Resource capacity versus demand
Answer: D
NEW QUESTION # 36
Which statement is true about Groups?
- A. They can have managers who are not members.
- B. They can be deleted.
- C. They can have duplicate names.
- D. They can be renamed.
Answer: A,C
NEW QUESTION # 37
You are a Portfolio Manager with a filter that has been set to identify and assign projects to your portfolio. You are in Primavera P6 EPPM Web Interface. How could you be certain that the list of projects in your portfolio is complete?
- A. by manually updating projects
- B. by manually refreshing the filter
- C. by manually hiding projects
- D. by manually adding new projects
Answer: B
NEW QUESTION # 38
Identify the true statement regarding project templates.
- A. They are created in the client and managed in the web.
- B. They are managed using Methodology Manager.
- C. They are created using Project Architect.
- D. They are managed in the web in the same database.
Answer: D
NEW QUESTION # 39
......