[Aug 29, 2021] Latest PRINCE2Foundation Exam with Accurate PRINCE2 Foundation written Exam PDF Questions
Practice To PRINCE2Foundation - Lead2PassExam Remarkable Practice On your PRINCE2 Foundation written Exam Exam
NEW QUESTION 100
Which are advantages of a clear end to a project?
1. No further costs will be incurred by the project
2. Project products will be transferred to operations and support
3. All benefits will have been achieved
4. The project brief will be re-baselined
- A. 1 and 4
- B. 3 and 4
- C. 2 and 3
- D. 1 and 2
Answer: D
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Closing_a_Project
NEW QUESTION 101
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
- A. Team Plan
- B. Work Package
- C. Product Description
- D. Stage Plan
Answer: B
NEW QUESTION 102
Identify the missing words in the following sentence.
The 'managing a stage boundary' process should be executed [ ? ] a management stage.
- A. when a stage plan has been prepared for
- B. at, or close to the end of,
- C. when all the delivery steps have been completed within
- D. at the beginning of
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: https://publications.axelos.com/Prince2Agile2015/content.aspx?
showNav=true&expandNav=true&page=cros_131
NEW QUESTION 103
Where should a team manager look for information about the quality required for a product?
- A. Team plan
- B. Project initiation documentation
- C. Product description
- D. Quality management approach
Answer: C
Explanation:
Explanation
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2
NEW QUESTION 104
Which is a minimum requirement for applying the change theme?
- A. To define the project's approach to baselining products
- B. To record every issue that is raised in the issue register
- C. To appoint the project manager as part of the change authority
- D. To establish a change budget to fund changes in scope
Answer: B
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Themes#Change_Theme
NEW QUESTION 105
Which is a responsibility of the project board?
- A. To ensure production of the project's outputs
- B. To implement the change control approach
- C. To manage the team managers and project support
- D. To ensure effective communication with external stakeholders
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Project_Board
NEW QUESTION 106
Which is a true statement about acceptance criteria?
- A. Once agreed, acceptance criteria CANNOT be changed
- B. Acceptance criteria should be agreed between the customer and the supplier
- C. Acceptance criteria are used to produce the customer's quality expectations
- D. Acceptance criteria are less specific and precise than customer's quality expectations
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 107
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A. Progress
- B. Organization
- C. Quality
- D. Change
Answer: A
Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-progress.php
NEW QUESTION 108
Identify the missing words in the following sentence. A purpose of the Plans theme is to [ ? ] the project's plans.
- A. summarize the results of the quality activities performed on
- B. define the project benefits to be achieved by each of
- C. define a coding system to provide a unique identifier for the products within
- D. provide a framework to design, develop and maintain
Answer: D
NEW QUESTION 109
Which is a purpose of the 'directing a project' process?
- A. To update the project plan before the next stage
- B. To exercise overall control over the project
- C. To do the minimum in order to decide whether the project is feasible
- D. To take corrective action to control risks and issues
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Directing_a_Project#Purpose
NEW QUESTION 110
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
- A. Ensure the technical integrity of a project
- B. Specify the desired result
- C. Provide the resources and skills to deliver the desired result
- D. Develop a project's products
Answer: B
NEW QUESTION 111
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
- A. The need to involve key stakeholders on the project management team
- B. Having insufficient time to perform the role
- C. Having insufficient authority to perform the role
- D. The preference of the Project Manager
Answer: B
NEW QUESTION 112
Which is a purpose of an Exception Plan?
- A. Define the changes which are within the scope of the change budget
- B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
- C. Identify the actions required to recover from the effect of a tolerance deviation
- D. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
Answer: C
NEW QUESTION 113
Which is a responsibility of the project board?
- A. To ensure production of the project's outputs
- B. To implement the change control approach
- C. To manage the team managers and project support
- D. To ensure effective communication with external stakeholders
Answer: D
Explanation:
Reference: http://prince2.wiki/Organization#Project_Board
NEW QUESTION 114
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.
- A. the project manager
- B. corporate, programme management or the customer
- C. the project board
- D. the change authority
Answer: C
Explanation:
Section: Volume B
Explanation/Reference:
NEW QUESTION 115
Which is NOT a requirement of a Stage Plan?
- A. Approved at the end of a management stage
- B. Produced near to the end of the previous management stage
- C. Approved and signed-off by Project Assurance
- D. Produced to an appropriate level of detail to enable day-to-day control
Answer: C
NEW QUESTION 116
Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
- A. Manage by exception
- B. Manage by stages
- C. Learn from experience
- D. Continued business justification
Answer: A
NEW QUESTION 117
Who are considered as the stakeholders in a project?
- A. Everyone in the corporate organization
- B. Only those who are users of the products
- C. Everyone involved in or affected by the project
- D. Only those benefitting the project
Answer: C
NEW QUESTION 118
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
- A. Themes
- B. Principles
- C. Techniques
- D. Processes
Answer: B
NEW QUESTION 119
According to the 'continued business justification' principle, what must project benefits be aligned to?
- A. The technology available
- B. The business objectives
- C. The direction of the project board
- D. Regular deliveries throughout the project
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-principle-continued-business-justification.php
NEW QUESTION 120
How are team managers involved in tailoring PRINCE2 suit the project?
- A. Team managers are accountable for the tailoring of the work packages
- B. Team managers may advice on tailoring to improve the management of work packages
- C. Team managers should document the tailoring of the work packages
- D. Team managers should not be involved in tailoring PRINCE2
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 121
......
Exam Questions and Answers for PRINCE2Foundation Study Guide Questions and Answers!: https://www.lead2passexam.com/PRINCE2/valid-PRINCE2Foundation-exam-dumps.html
Practice To PRINCE2Foundation - Lead2PassExam Remarkable Practice On your PRINCE2 Foundation written Exam Exam: https://drive.google.com/open?id=1oLOgnJU5ZLgsIu1H_N39X7ghin0Caub8